冷再生機的馬達與減速機結合安裝步驟
來源:http://www.cifrimas.com/ 日期:2023-04-14 發布人:guanli
以施工速度快,效率高,受天氣影響小,性能穩定、應用廣泛而倍受客戶稱贊的冷再生機,足跡已經遍布到各地。那你對此設備了解多少呢?下面冷再生機出租廠家就來講講--冷再生機的馬達與減速機結合安裝步驟。
The cold recycling machine, which is highly praised by customers for its fast construction speed, high efficiency, minimal weather impact, stable performance, and wide application, has a footprint spread throughout the country. How much do you know about this device? Below, the rental manufacturer of the cold regeneration machine will talk about the installation steps of the motor and reducer combination of the cold regeneration machine.
步驟:
Step:
1、將設備啟動移至已選好場地,將轉子罩彈簧銷軸取出,再將轉子放置低點,切記不可懸置或有吃力現象,造成大臂油缸銷軸取不出來,油管泄壓易出危險。
1. Start the equipment and move it to the selected site. Take out the spring pin of the rotor cover, and then place the rotor at a low point. Remember not to suspend or exert force, which may cause the pin of the boom oil cylinder to not be removed and the oil pipe may be in danger of pressure relief.
2、拆卸油管和轉子馬達的保護罩殼。
2. Remove the protective cover of the oil pipe and rotor motor.
3、將馬達到工作泵的6根油管在大臂連接處全部拆卸開,并用衛生紙和塑料帶將接口全部封緊,預防進入灰塵及雜物,并取下連接鋼管。
3. Disassemble all 6 oil pipes from the motor to the working pump at the connection point of the boom, and seal all interfaces tightly with toilet paper and plastic tape to prevent dust and debris from entering. Remove the connecting steel pipe.
4、卸掉馬達上的螺栓,并取下馬達,注意需要兩個人必須輕拿輕放。
4. Remove the bolts from the motor and remove the motor, taking care that two people must handle it gently.
5、將轉子罩殼所有的連接桿拆卸,取下銷軸。
5. Remove all connecting rods of the rotor housing and remove the pin shaft.
6、將連接兩個大臂與固定橫桿上的螺栓拆卸掉,只留兩邊上面的4個。
6. Remove the bolts connecting the two large arms and the fixed crossbar, leaving only four on both sides.
7、拆掉橫桿和車體連接的4個螺栓,上下面做好標記,方便安裝。
7. Remove the four bolts connecting the crossbar and the vehicle body, and mark the upper and lower parts for easy installation.
8、用吊車掛轉子一側的大臂處,另一側掛馬達后側的銷軸,先提升盡大量向一側移動,然后將兩根鋼絲繩均掛到出來的那一側,拖至外面。
8. Use a crane to hang the large arm on one side of the rotor and the pin shaft on the back of the motor on the other side. First, lift as much as possible and move it to one side. Then, hang both steel wire ropes onto the side where they come out and drag them outside.


9、卸掉滑靴,吊出轉子罩。
9. Remove the sliding shoes and lift out the rotor cover.
10、卸掉大臂與橫桿和轉子的連接處的螺栓,吊出大臂,放置一邊。
10. Remove the bolts at the connection between the boom and the crossbar and rotor, lift out the boom, and place it aside.
11、卸掉減速機固定螺絲,并用撬棍插入軸套壓住,用吊車吊出減速機,放置一邊,檢查有無滲漏現象。
11. Remove the fixing screws of the reducer and insert a pry bar into the shaft sleeve to press it down. Use a crane to lift out the reducer and place it aside to check for any leakage.
12、放開減速機的兩個油堵,放凈廢油。因兩個油堵成90度角,在加注新油時,減速機平放的基礎上必須讓注油孔在高點,直到觀察孔漏油為止,然后將油堵纏上生料帶上緊,如油堵是無‘O’型圈的類型,需在生料帶的外面涂抹密封膠,觀察12小時后有無滲漏現象。
12. Release the two oil plugs of the gearbox and drain the waste oil. Since the two oil plugs form a 90 degree angle, when filling new oil, the oil filling hole must be kept at a high point on the basis of the reducer placed horizontally until the observation hole leaks oil, and then the oil plug is wrapped around the Thread seal tape and tightened. If the oil plug is of the type without an 'O' ring, it is necessary to apply sealant on the outside of the Thread seal tape and observe whether there is leakage after 12 hours.
13、將以上步驟反之,安裝完畢。
13. Reverse the above steps to complete the installation.
在安裝的過程中,大臂、馬達、減速機的固定螺栓均需涂抹緊固膠,馬達與減速機結合面涂抹密封膠。更多相關內容就來我們網站http://www.cifrimas.com咨詢!
During the installation process, the fixing bolts of the boom, motor, and reducer need to be coated with fastening adhesive, and the joint surface between the motor and reducer needs to be coated with sealant. For more related content, come to our website http://www.cifrimas.com consulting service
下一篇:就地冷再生機是什么及技術適用條件 上一篇:天氣清冷之前冷再生機如何進行保養
推薦閱讀/ Recommended reading
- 就地冷再生機是什么及技術適用條件 2023-04-17
- 冷再生機的馬達與減速機結合安裝步驟 2023-04-14
- 天氣清冷之前冷再生機如何進行保養 2023-04-14
- 如何確保水泥撒布車安全使用和有效維護? 2023-04-12
現今26噸壓路機保養存在的誤區!
[2018-08-23]
對于26噸壓路機的維修保養十分重要,但是由于技術保養人員對保養工作存在的誤區,致使26噸壓路機性能更加不良。下面冷再生機租賃廠家從五個
推薦產品/ Recommended products
久久精品这里热有精品